oneCorp GmbH - Datacenter Maintenance DUS5 – Maintenance details

Datacenter Maintenance DUS5

Completed
Scheduled for April 03, 2025 at 8:00 AM – 11:00 AMUTC

Affects

Datacenter

Under maintenance from 8:00 AM to 11:00 AM

Updates
  • Completed
    April 03, 2025 at 11:00 AMUTC
    Completed
    April 03, 2025 at 11:00 AMUTC
    Maintenance has completed successfully
  • In progress
    April 03, 2025 at 8:00 AMUTC
    In progress
    April 03, 2025 at 8:00 AMUTC
    Maintenance is now in progress
  • Planned
    April 03, 2025 at 8:00 AMUTC
    Planned
    April 03, 2025 at 8:00 AMUTC

    We would like to inform you that the Datacenter will be conducting a Black Building Test on Thursday, April 03, 2025, at 10:00. This will affect the location DUS5, and the expected duration for the tests is approximately 3 hours.

    The purpose of this test is to verify the functionality of the emergency power infrastructure under realistic conditions. The tests will be carried out under controlled conditions, so no interruption of the power supplies of the IT systems is expected.