oneCorp GmbH - Maintenance Datacenter Infrastructure - DUS1 – Maintenance details

Maintenance Datacenter Infrastructure - DUS1

Completed
Scheduled for September 02, 2026 at 6:00 AM – September 03, 2026 at 12:00 PMUTC

Affects

Datacenter

Under maintenance from 6:00 AM to 12:00 PM

Updates
  • Completed
    September 03, 2026 at 12:00 PMUTC
    Completed
    September 03, 2026 at 12:00 PMUTC
    Maintenance has completed successfully
  • In progress
    September 02, 2026 at 6:00 AMUTC
    In progress
    September 02, 2026 at 6:00 AMUTC
    Maintenance is now in progress
  • Planned
    August 25, 2026 at 1:44 PMUTC
    Planned
    August 25, 2026 at 1:44 PMUTC

    Dear customer,

    As part of our ongoing efforts to further optimize our technical infrastructure and maintain our high level of service quality, the control system of the emergency power supply at our DUS1 site in Düsseldorf, Germany, will be replaced.

    The maintenance is scheduled to take place from September 02, 2026, at 8:00 a.m. until approximately 2:00 p.m. on September 03, 2026.

    During this period, the emergency power supply system will be out of service for approximately six hours. However, a temporary replacement generator will be provided to ensure continuous availability. Because this work has been carefully prepared with appropriate technical and organizational measures, no impact on regular operations is expected.

    We appreciate your patience and understanding while these improvements are being implemented.

    Thank you for your cooperation.