APR2
Datacenter Maintenance DUS6
Completed·April 02, 2025 at 10:30 AM – 12:00 PMUTC
Affects
Datacenter
Under maintenance from 10:30 AM to 12:00 PM
·
- Completed · April 02, 2025 at 12:00 PMUTCMaintenance has completed successfully
- In progress · April 02, 2025 at 10:30 AMUTCMaintenance is now in progress
- Planned · April 02, 2025 at 10:30 AMUTC
We would like to inform you that the Datacenter will be conducting a Black Building Test on Wednesday, April 2, 2025, at 12:30. This will affect the location DUS6, and the expected duration for the tests is approximately 1.5 hours.
The purpose of this test is to verify the functionality of the emergency power infrastructure under realistic conditions. The tests will be carried out under controlled conditions, so no interruption of the power supplies of the IT systems is expected.